Half the timeline happens before anyone picks up a hammer
People ask how long a renovation takes and mean the time with trades in the house. The honest answer starts earlier. Drawings and engineering take weeks, a building permit takes weeks more, a planning permit where one is needed takes months, and a good builder is rarely free the week the permit arrives. On a typical project the planning runs about as long as the build. The calculator keeps the two apart so you can see which one is actually setting your finish date.
| Stage on site | Typical weeks | What holds it up |
|---|---|---|
| Demolition and strip-out | 1 | Asbestos, services to disconnect |
| Structure, framing, roof | 2 to 6 | Weather, steel, window delivery |
| Rough-in | 1 to 2 | Frame inspection, late selections |
| Insulation and plaster | 2 | Drying time in winter |
| Waterproofing and tiling | 2 | Membrane cure, tile delivery |
| Kitchen, joinery, benchtops | 2 | Stone is templated after cabinets go in |
| Painting | 1 to 2 | Other trades still in the room |
| Flooring | 1 | Acclimatising timber, slab moisture |
| Fit-off and clean | 1 to 2 | Defects, final inspection |
What actually moves the date
Three things, and all of them are decided early. Selections: every tap, tile, light and handle chosen before the job starts is a delay that cannot happen. Long-lead orders: windows, custom joinery and benchtops can take six to ten weeks to make, so they are ordered at the start, not when the room is ready. And changes: a variation in week six stops the trades who were booked for week seven. Weather only matters until the roof is on, and the unknowns inside old walls are what the delay allowance is for.
Worked example
With the default figures, planning takes 6 + 6 + 6 = 18 weeks. Construction stages total 15.5 weeks, and a 15 percent allowance makes it 17.8. Starting the drawings in early October puts the start on site in early February and completion in mid-June, about 36 weeks or eight months from the first meeting. Start the same job in July and it crosses Christmas, adding three weeks.
Common questions
How long does a renovation take?
Three to six weeks for a bathroom or kitchen on site; four to eight months for a whole house, plus planning.
How long for a permit?
Two to six weeks for a building permit; three to six months more if a planning permit is needed.
Why do they run late?
Late selections, long-lead items ordered late, hidden problems, weather and variations.
Christmas shutdown?
From the week before Christmas to mid-January. Allow three weeks.
A planning estimate. Your builder's programme, the permit authority and the weather set the real dates.