Renovation budget planner

Enter your own quotes and allowances. The planner adds a contingency, sorts out the GST and shows the total, the per square metre figure and the biggest item.

A budget is the quotes, plus what the quotes leave out, plus a reserve

Most renovation budgets go wrong in the same three places. The quotes are not on the same basis, some with GST and some without, some including the fittings and some with an allowance. The costs outside the building contract are forgotten: design, engineering, the permit, appliances, window furnishings, somewhere to live. And there is no reserve for what demolition finds. This planner is a plain adding machine for your own figures that forces each of those into the open: one GST setting, a line for fees and for everything else, and a contingency that is added as a visible number.

budget = (sum of quotes and allowances) × (1 + contingency), with GST counted once

ProjectContingencyWhy
New extension, full drawings and engineering10%Few unknowns once the footings are in
Kitchen or bathroom in a newer house10 to 15%Plumbing and wiring behind walls
Whole-house renovation15%Many trades, many junctions with old work
Period house, structural changes, restumping20%Rot, asbestos, old wiring, undersized framing

Getting quotes onto the same basis

Before adding quotes together, check four things on each. Whether it includes GST. What the allowances are, since a prime cost item of a few hundred dollars for tapware you intend to spend more on is a variation waiting to happen. What is excluded, usually in small print at the end: rubbish removal, painting, making good, asbestos, rock. And how long the price holds. A quote that is cheaper because it leaves things out is not cheaper.

What a builder allows We carry a contingency inside our own price for the things we can foresee, and we tell clients to hold a separate one of their own for the things nobody can and for the changes they will make, because every client makes some. The reserve is not spent on upgrades in week two. If it is untouched when the plaster is on, most of the unknowns are behind you and it can go to the things you wanted. Victorian law also caps the deposit a builder can take, and work over $20,000 needs domestic building insurance, so a quote that ignores either is one to question.

Worked example

Suppose the figures you enter add up to $100,000 including GST, and the house is sixty years old, so the contingency is 20 percent. The planner shows a $20,000 reserve and a budget of $120,000, of which $10,909 is GST. If the same figures had been ex GST, the budget would be $132,000. That $12,000 gap is the size of mistake that mixing GST bases makes.

Common questions

How much contingency?

10 percent on new work, 15 on a typical renovation, 20 on an old house.

What gets forgotten?

Fees and permits, somewhere to live, appliances, window furnishings, and items chosen after the quote.

Do quotes include GST?

Quotes to homeowners must. Trade and supplier prices often do not. Check each one.

Prime cost and provisional sums?

Allowances, not prices. If the real cost is higher you pay the difference.

An adding tool for your own figures, not a price guide and not financial advice. Get written quotes, and check contract, deposit and insurance requirements in your state.