A loan that grows as the house does
When you buy an existing house the whole loan is drawn on settlement day. When you buy land and build, it is not. The land part is drawn when the land settles. The building part is paid to the builder in stages, each one released when that stage of the house is finished. Interest is charged only on what has been drawn so far, usually as interest-only repayments, so the monthly cost starts small and climbs with every stage. When the house is complete, the loan becomes an ordinary principal and interest loan for the full amount.
| Stage | Share of contract | Drawn | Loan balance | Interest a month |
|---|---|---|---|---|
| Land settles | $230,000 | $230,000 | $1,150 | |
| Deposit | 5% | $22,500 | $252,500 | $1,263 |
| Base | 10% | $45,000 | $297,500 | $1,488 |
| Frame | 15% | $67,500 | $365,000 | $1,825 |
| Lock-up | 35% | $157,500 | $522,500 | $2,613 |
| Fixing | 25% | $112,500 | $635,000 | $3,175 |
| Completion | 10% | $45,000 | $680,000 | $4,077* |
$400,000 land, $450,000 build, $170,000 of your own money, 6 percent. *After completion: principal and interest over 30 years.
The cost nobody quotes you
Neither the land agent nor the builder quotes the interest you pay while the house is being built, and it is real money: about $22,100 in the example, $3,450 of it before a sod is turned, while the plans go through permits. It is paid month by month out of your own pocket, on top of rent. Two things move it. Time: the same build taking twelve months instead of nine costs about $6,200 more in interest. And when the big stages fall, since lock-up alone is 35 percent of the contract.
What changes the numbers
Your own contribution goes in first, so a larger deposit delays the first draw as well as shrinking the loan. Owning the land already removes the holding interest and the land loan altogether. A longer wait between land settlement and the slab adds interest on the land with nothing to show for it, which is the best argument for having drawings and permits well advanced before settling. The stage percentages here follow the standard Victorian domestic building contract; other states and custom contracts differ, and your contract's own schedule is what the lender follows.
Worked example
Land $400,000 and a $450,000 building contract, $850,000 in total, with $170,000 of your own money: a $680,000 loan, 80 percent. The cash goes into the land, leaving a $230,000 land loan at $1,150 a month. Three months of waiting costs $3,450. Over a nine month build the draws add $18,653 of interest, $22,103 in all. The last interest-only payment is $3,175, and after handover the repayment is $4,077 a month over 30 years.
Common questions
How does a construction loan work?
The building part is paid out in stages. You pay interest only on what has been drawn until the house is finished.
How much interest during the build?
About $22,000 in the example: a year at 6 percent on a loan that grows from $230,000 to $680,000.
Rent and a mortgage at once?
Usually. The total peaks in the last couple of months before handover.
What does the lender need first?
A fixed-price contract, approved plans and permit, the builder's insurance, and your own money in first.
General information and arithmetic only. It does not consider your objectives, financial situation or needs, is not financial advice or a credit quote, and does not represent any lender's product. Stage schedules, rates, fees and lending rules vary; confirm with your lender or a licensed broker and your building contract.