Calculators › Concrete & footings

Concrete column and pier calculator

Round or square columns, piers and pad footings: cubic metres, 20 kg bags and premix to order, for any number of them.

Columns, piers and pads are all one sum

A round pier, a concrete column and a square pad footing are the same calculation with different numbers: the area of the cross-section times its height or depth. Round sections use π × radius², square ones width × depth. The only judgement is the waste. A column cast in a form tube comes out at exactly the size of the tube, but a pier hole drilled by an auger is always a little bigger than the auger and a little rougher, and hand-dug holes are bigger again.

round: π × (diameter ÷ 2)² × height · square: width × depth × height

Sectionm³ per metre20 kg bags per metre
200 mm round0.0313.4
300 mm round0.0717.6
450 mm round0.15917.1
600 mm round0.28330.4
300 × 300 mm square0.0909.7
450 × 450 mm square0.20321.8

Before waste, at 0.0093 m³ per 20 kg bag.

Piers under a house or deck

Bored piers under a slab edge, a deck or a stumped floor are the commonest use of this calculator. The engineer gives the diameter and a minimum depth into firm ground, and the depth on the day is whatever it takes to reach it, so the order is an estimate until the holes are dug. Count the piers, use the design depth, and allow a little extra for the ones that go deeper.

What a builder allows We measure every pier hole after it is dug and before the concrete is ordered, because two holes on the same site can differ by half a metre where the clay changes. Then we order the measured volume plus about 10 percent, and keep a few bags on site for the last hole. With form tubes the number is exact, so the extra is only for spillage and the barrow.

Worked example

Four round piers, 300 mm diameter and 1.2 m deep. Each is π × 0.15² × 1.2 = 0.085 m³; four are 0.339 m³, and with 10 percent waste 0.373 m³. That is 41 bags of 20 kg, about 11 per pier, or 0.4 m³ of premix. A small job like this is usually bags.

Common questions

How much concrete is in a round column?

π × radius² × height. A 300 mm column is about 0.071 m³ per metre.

How many bags for a pier hole?

About 11 × 20 kg bags for a 300 mm pier 1.2 m deep, with waste.

How much concrete in a square column?

Width × depth × height. 300 × 300 × 2400 mm is 0.216 m³.

Bags or premix for piers?

Bags for a handful; compare premix over about half a cubic metre.

Quantities are estimates for ordering, not structural design. Pier and column sizes, depths and reinforcement come from your engineer's drawings.