Retention calculator

How much is held back from this claim, the running total against the contract cap, and what comes back at practical completion and after the defects period.

Ten percent of each claim, up to five percent of the job

Retention is money the paying party holds back from progress claims as security that the work will be finished and the defects fixed. The standard Australian arrangement, written into most head contracts and passed down to subcontracts, is 10 percent of each claim until the total withheld reaches 5 percent of the contract sum, then nothing further. On a $500,000 contract the cap is $25,000 and it is reached once $250,000 has been claimed, so the first half of the job carries the full deduction and the second half none.

held after this claim = min((claimed to date + this claim) × rate, contract sum × cap)

ClaimClaimed to dateRetention on claimTotal held
1: $80,000$80,000$8,000$8,000
2: $120,000$200,000$12,000$20,000
3: $60,000$260,000$5,000$25,000 (cap)
4: $140,000$400,000$0$25,000
5: $100,000$500,000$0$25,000

$500,000 contract, 10 percent per claim, 5 percent cap. Claim 3 only carries $5,000 because that is all that remains under the cap.

Getting it back

Half is usually released at practical completion and the rest at the end of the defects liability period, 12 months for most building contracts and shorter for trade subcontracts. Neither release is automatic: the contract will want a written claim, often with a final certificate or a defects sign-off attached, and the money is a debt like any other if it is not paid. Diarise the defects end date the day practical completion is certified, because nobody else will remind you.

What a builder allows Victorian domestic building contracts do not use retention: the client's protection is the staged payment schedule under the Domestic Building Contracts Act, and we cannot hold retention from a homeowner either. Retention lives on our commercial jobs and in our subcontracts, where we hold it on the same terms the head contract holds it on us, and no harder. On a subcontract we release the trade's half at PC the week we receive ours, since a subbie waiting on $5,000 for a year remembers it.

Cash, guarantees and trusts

Retention is your cash sitting in someone else's account for up to a year after you finish, which is why the cash flow gap calculator says to add it to your buffer. Most commercial contracts let you replace it with an unconditional bank guarantee for the same amount, which costs a fee but leaves the cash in the business. Some states have begun requiring retention money to be held in trust for larger projects; check the current rules for yours, since they change.

Worked example

A $500,000 contract, 10 percent retention, 5 percent cap, $200,000 claimed so far and a $60,000 claim this month. Held before this claim: $20,000. Held after: the smaller of $26,000 and the $25,000 cap, so $25,000. Retention on this claim $5,000, payable $55,000 ex GST, $60,500 inc. At PC $12,500 comes back, and the other $12,500 twelve months later.

Common questions

How is retention calculated?

A percentage of each claim, usually 10, until the total reaches the cap, usually 5 percent of the contract sum.

When is it released?

Commonly half at practical completion and half at the end of the defects period, on a written claim.

GST on retention?

GST applies to it; when it is attributed depends on your accounting basis. Ask your accountant.

Bank guarantee instead?

Often allowed for the same amount. Fee instead of cash tied up.

General arithmetic, not legal advice. Your contract sets the rate, cap, release terms and defects period; Security of Payment legislation in your state may affect how and when retention can be claimed.